Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.
had no notice.
California Civil Code — §§ 8450-8458
Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.
had no notice.
Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.
A mortgage or deed of trust, otherwise subordinate to a lien under Section 8450, has priority over a lien for work provided after recordation of a payment bond that satisfies all of the following requirements:
less than 75 percent of the principal amount of the mortgage or deed of trust.
Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.
If a site improvement is provided for in a direct contract separate from the direct contract for the remainder of the work of improvement, the site improvement is deemed a separate work of improvement and commencement of the site improvement is not commencement of the remainder of the work of improvement.
Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.
of all advances does not exceed the amount of the original construction loan.
Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.
unrecorded at the commencement of the site improvement and of which the claimant had no notice.
if a payment bond in an amount not less than 50 percent of the principal amount of the mortgage or deed of trust is recorded before completion of the work of improvement.