§ 8814

Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.
(a)If a direct contractor has withheld a retention from one or more subcontractors, the direct contractor shall, within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor’s share of the payment.
(b)If a retention received by the direct contractor

is specifically designated for a particular subcontractor, the direct contractor shall pay the retention payment to the designated subcontractor, if consistent with the terms of the subcontract.

(c)If a good faith dispute exists between the direct contractor and a subcontractor, the direct contractor may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.

Other sections in Article 2 - Retention Payment

This content is for reference, learning, and study purposes only. All legal text should be verified against the official California Legislative Information website, which is the authoritative source for California law. Data last processed: February 17, 2026.