§ 65950.1

Added by Stats. 1983, Ch. 1240, Sec. 1.

Notwithstanding Section 65950, if there has been an extension of time pursuant to Section 21100.2 or 21151.5 of the Public Resources Code to complete and certify the environmental impact report, the lead agency shall approve or disapprove the project within 90 days after certification of the environmental impact report.