(a)Except as provided in this section, a person shall not conduct surface mining operations unless a permit is obtained from, a reclamation plan has been submitted to and approved by, and financial assurances for reclamation have been approved by the lead agency for the operation pursuant to this article.
(b)A person with an existing surface mining operation who has vested rights pursuant to Section 2776 and who does not have an approved reclamation plan shall submit a reclamation plan to the lead agency not later than March 31, 1988. If a reclamation plan application is not on file by March 31, 1988, the continuation of the surface mining operation is prohibited until a reclamation plan is

submitted to the lead agency. For the purposes of this subdivision, a reclamation plan existing prior to January 1, 2017, may consist of all or the appropriate sections of any plans or written agreements previously approved by the lead agency or another agency, together with any additional documents needed to substantially meet the requirements of Sections 2772 and 2773 and the lead agency surface mining ordinance adopted pursuant to subdivision (a) of Section 2774, provided that all documents, which together were proposed to serve as the reclamation plan, are submitted for approval to the lead agency in accordance with this chapter.

(c)[Reserved]
(d)[Reserved]
(e)(1) A person who can

substantiate, based on the evidence of the record, that a lead agency has either (A) failed to act according to due process or has relied on considerations not related to the specific applicable requirements of Sections 2772, 2772.1, 2773, 2773.1, 2773.3, and 2773.4 and the lead agency surface mining ordinance adopted pursuant to subdivision (a) of Section 2774 in reaching a decision to deny approval of a reclamation plan or financial assurances for reclamation, or (B) failed to act within a reasonable time of receipt of a completed application may appeal that action or inaction to the board.

(2)The supervisor may appeal a lead agency’s approval of a financial assurance cost estimate to the board if the supervisor has commented pursuant to Section 2773.4 that the financial assurance cost estimate is inadequate based on consideration of the

following:

(A)Section 2773.1.
(B)Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations.
(C)The board’s financial assurance guidelines adopted pursuant to subdivision (f) of Section 2773.1.
(3)If the approved financial assurance cost estimate applies to a reclamation plan approved for a new surface mining operation, an expanded surface mining operation, or an interim financial assurance cost estimate due to an order to comply, stipulated or otherwise, the operator shall provide a financial assurance mechanism pursuant to subdivision (e) of Section 2773.4 in the amount

of the approved financial assurance cost estimate, notwithstanding an appeal filed pursuant to this subdivision and subject to modification pending the outcome of the appeal.

(4)If the approved financial assurance cost estimate is an update to an existing approved financial assurance cost estimate, the existing financial assurance mechanism shall remain in place and shall not be adjusted until a final determination by the board on the appeal filed pursuant to this subdivision.
(f)(1) The board may decline to hear an appeal if it determines that the appeal raises no substantial issues related to the lead agency’s decision to deny the approval of a reclamation plan or financial assurance, or the timeliness in reviewing a completed application. Appeals filed by

the supervisor shall be heard by the board.

(2)If the board takes up an appeal, the appeal shall be scheduled and heard at a public hearing within 45 days of the board’s receipt of a complete administrative record, or a longer period as may be mutually agreed to by the board, the appellant, and the operator, or, if the appeal is filed by the supervisor, by the board, the supervisor, and the operator.
(g)(1) (A) When hearing an appeal filed pursuant to paragraph (1) or (2) of subdivision (e), the board shall determine whether the reclamation plan or the financial assurance cost estimate substantially meets the applicable requirements of Sections 2772, 2772.1, 2773, 2773.1, 2773.3, and 2773.4; Article 1 (commencing with Section 3500),

Article 9 (commencing with Section 3700), and Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations; and the lead agency’s surface mining ordinance adopted pursuant to subdivision (a) of Section 2774. The board shall approve or uphold a reclamation plan or financial assurance cost estimate determined to meet those applicable requirements. In any event, financial assurances for reclamation shall be sufficient to perform reclamation of lands remaining disturbed.

(B) For purposes of this subdivision, “substantially” means actual compliance in respect to the substance and form requirements essential to the objectives of this chapter.

(2)(A) A reclamation plan determined not to meet the applicable

requirements of Sections 2772, 2772.1, 2773, 2773.1, 2773.3, and 2773.4; Article 1 (commencing with Section 3500), Article 9 (commencing with Section 3700), and Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations; and the lead agency’s surface mining ordinance adopted pursuant to subdivision (a) of Section 2774 shall be returned to the operator with a notice of deficiencies. The operator shall be granted, once only, a period of 30 days or a longer period mutually agreed upon by the operator and the board to do both of the following:

(i)Correct the noted deficiencies.

(ii) Submit the revised reclamation plan to the lead agency for review and approval.

(B) Within 10 days of the hearing, the board shall provide notice via certified mail to the lead agency, the operator, and the Division of Mine Reclamation of the board’s determination. The notice shall include instructions to the operator to submit to the lead agency for approval a revised reclamation plan consistent with the board’s determination.

(3)(A) If the board determines the lead agency’s approved financial assurance cost estimate does not meet the requirements of Sections 2773.1 and 2773.4, Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, and the board’s financial assurance guidelines adopted pursuant to subdivision (f) of Section 2773.1, the board shall note the deficiencies and, based on the record, include adequate

cost estimates for each noted deficiency.

(B)Within 10 days of the hearing, the board shall provide notice via certified mail to the lead agency, the operator, and the Division of Mine Reclamation of the board’s determination with instructions to the operator to submit to the lead agency for approval a revised financial assurance cost estimate consistent with the board’s determination. The instructions shall include a reasonable submission deadline of not less than 30 days.
(C)The lead agency shall approve the revised financial assurance cost estimate. That approval shall supersede and void the prior approved financial assurance cost estimate.
(D)A financial assurance mechanism shall be established by the operator

pursuant to subdivision (e) of Section 2773.4 following the approval of the financial assurance cost estimate.

(E)The failure of the operator to submit to the lead agency a revised financial assurance cost estimate consistent with the board’s determination and deadline may be grounds for the issuance of an order to comply pursuant to subdivision (a) of Section 2774.1.
(h)(1) Within 90 days of a surface mining operation becoming idle, as defined in Section 2727.1, the operator shall submit an interim management plan to the lead agency for review. The review and approval of an interim management plan shall not be considered a project for purposes of the California Environmental Quality Act (Division 13 (commencing with Section 21000)). The approved interim

management plan shall be considered an amendment to the surface mining operation’s approved reclamation plan for purposes of this chapter. The interim management plan shall only provide for necessary measures the operator will implement during its idle status to maintain the site in compliance with this chapter, including, but not limited to, all permit conditions.

(2)The interim management plan may remain in effect for a period not to exceed five years, at which time the lead agency shall do one of the following:
(A)Renew the interim management plan for an additional period not to exceed five years, which may be renewed for one additional five-year renewal period at the expiration of the first five-year renewal period, if the lead agency finds that the surface mining operator

has complied fully with the interim management plan.

(B)Require the operator to commence reclamation in accordance with its approved reclamation plan.
(3)The financial assurances required by Section 2773.1 shall remain in effect during the period that the surface mining operation is idle. If the surface mining operation is still idle after the expiration of its interim management plan, the operator shall commence reclamation in accordance with its approved reclamation plan.
(4)(A) Within 45 days of the receipt of the interim management plan, the lead agency shall review the interim management plan in accordance with its ordinance adopted pursuant to subdivision (a) of Section 2774, and if the

interim management plan satisfies the requirements of this section, forward the plan to the supervisor for comment. Otherwise, the lead agency shall notify the operator in writing of any deficiencies in the interim management plan. The operator shall have 30 days, or a longer period mutually agreed upon by the operator and the lead agency, to submit a revised interim management plan.

(B)The lead agency shall submit the interim management plan, including a revised interim management plan, to the supervisor for review and certify to the supervisor that the interim management plan is a complete submission and complies with all of the following requirements:
(i)The applicable requirements of this chapter.

(ii) Article 1 (commencing with Section 3500) and Article 9 (commencing with Section 3700) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, as applicable.

(iii) The lead agency’s surface mining ordinance in effect at the time that the interim management plan is submitted to the

supervisor for review, except if the board is the lead agency.

(C) After receipt of the certified complete interim management plan, the supervisor shall have 30 days to prepare written comments on the interim management plan, if he or she elects to do so.

(D) The lead agency shall review and evaluate written comments received from the supervisor relating to the interim management plan within a reasonable amount of time.

(E) The lead agency shall prepare a written response to the supervisor’s comments received pursuant to subparagraph (C) describing the disposition of the major issues raised by the comments. The lead agency shall submit its response to the supervisor and the operator at least 30 days prior to the

intended approval of the interim management plan. The lead agency’s response shall include either of the following:

(i)A description of how the lead agency proposes to adopt the supervisor’s comments to the interim management plan.

(ii) A detailed description of the reasons why the lead agency proposes not to adopt the supervisor’s comments.

(F) Where the supervisor has commented, the lead agency shall give the supervisor at least 30 days’ written notice of the time, place, and date of the hearing at which the interim management plan is scheduled to be approved by the lead agency, or, if no hearing is required by this chapter, the local ordinance, or other law, the lead agency shall provide 30 days’ written notice to the supervisor

that the lead agency intends to approve the interim management plan.

(G) Within 30 days following the approval of the interim

management plan, the lead agency shall provide the supervisor notice of the approval and a copy of the approved interim management plan.

(5)The lead agency shall approve or deny approval of the interim management plan within 60 days of receipt of the supervisor’s comments or within 90 days of submitting the interim management plan to the supervisor if no comments are received from the supervisor. If the lead agency denies approval of the interim management plan, the operator may appeal that action to the lead agency’s governing body, which shall schedule a public hearing within 45 days of the filing of the appeal or a longer period mutually agreed upon by the operator and the governing body.
(6)Unless review of an interim management plan is pending before

the lead agency or an appeal is pending before the lead agency’s governing body, a surface mining operation that remains idle for over one year after becoming idle, as defined in Section 2727.1, without obtaining approval of an interim management plan shall be considered abandoned and the operator shall commence and complete reclamation in accordance with the approved reclamation plan.

(i)An enforcement action that may be brought against a surface mining operation for operating without an approved reclamation plan, financial assurance, or interim management plan shall be held in abeyance pending review pursuant to subdivision (b) or (h), or the resolution of an appeal filed with the board pursuant to subdivision (e), or with a lead agency governing body pursuant to subdivision (h).

Added by Stats. 2016, Ch. 8, Sec. 5. (SB 209) Effective January 1, 2017.

For the purposes of a borrow pit surface mining operation that is owned or operated by a lead agency solely for use by that lead agency, all of the following shall apply:

(a)(1) In addition to the requirements of Sections 2772 and 2773, the lead agency shall include in its reclamation plan maintenance measures that become effective when the borrow pit surface mining operation is idle. The maintenance measures shall maintain the site in compliance with this chapter while the borrow pit surface mining operation is idle.
(2)Notwithstanding paragraph (1), a lead agency may obtain an interim management plan pursuant to subdivision (h) of Section 2770.
(3)A lead agency that complies with this subdivision shall be exempt from the requirements of paragraph (6) of subdivision (h) of Section 2770.
(b)Notwithstanding paragraph (2) of subdivision (h) of Section 2770, an interim management plan for a borrow pit surface mining operation may remain in effect until reclamation of the borrow pit surface mining operation is completed in accordance with the approved reclamation plan.
(c)Notwithstanding subdivision (b) of Section 2774, a lead agency may conduct an inspection of a borrow pit surface mining operation once every two calendar years during a period when the borrow pit surface mining operation is idle.

Added by Stats. 1984, Ch. 254, Sec. 1.

Whenever surface mining operations are proposed in the 100-year flood plain for any stream, as shown in Zone A of Flood Insurance Rate Maps issued by the Federal Emergency Management Agency, and within one mile, upstream or downstream, of any state highway bridge, the lead agency receiving the application for the issuance or renewal of a permit to conduct the surface mining operations shall notify the Department of Transportation that the application has been received. The Department of Transportation shall have a period of not more than 45 days to review and comment on the proposed surface mining operations with respect to any potential damage to the state highway bridge from the proposed surface mining operations. The lead agency shall not issue or renew the permit until the Department of Transportation has submitted its comments or until 45 days from the date the application for the permit was submitted, whichever occurs first.

Added by Stats. 2000, Ch. 515, Sec. 1. Effective January 1, 2001.

(a)Whenever surface mining operations are proposed within the boundaries of the San Gabriel Basin Water Quality Authority that may penetrate the groundwater, and whenever proposed reclamation activities may impact groundwater quality, the lead agency reviewing an application to conduct surface mining operations, or reviewing an application for the approval of a reclamation plan, shall notify and provide copies of the subject application to the appropriate California regional water quality control board, and any watermaster for the groundwater recharge basin. Notwithstanding any other provision of law, the appropriate California regional water quality control board may impose an administrative fee on the applicant to cover its costs associated with the review of, and preparation of, comments on the subject application, as required pursuant to this section.
(b)Each agency shall have 60 days to review and comment on the proposed surface mining operation described in subdivision (a) and the adoption of any reclamation plan therefor. Each agency shall comment on the existing groundwater quality and the potential impacts to water quality that may result from the mining operations and the proposed reclamation plan, and shall recommend methods and procedures to protect groundwater quality and prevent groundwater degradation. Each agency shall also comment on the proposed mining activities, including the conduct of excavation and backfilling operations in contact with groundwater, and the impact of any proposed alternative land uses on groundwater quality. When the proposed surface mining operations or reclamation plan will impact the groundwater, the lead agency shall not approve the reclamation plan without requiring actions to ensure the reasonable protection of the beneficial uses of groundwater and the prevention of nuisance. Each agency shall have 60 days to review and comment or until 60 days from the date of application, whichever occurs first.
(c)This section applies to activities otherwise subject to this chapter conducted within the boundaries of the San Gabriel Basin Water Quality Authority. To the extent of any conflict between this section and any other provision of this chapter, this section shall prevail.

Repealed and added by Stats. 1990, Ch. 1097, Sec. 10.

Whenever a proposed or existing surface mining operation is within the jurisdiction of two or more public agencies, is a permitted use within the agencies, and is not separated by a natural or manmade barrier coinciding with the boundary of the agencies, the evaluation of the proposed or existing operation shall be made by the lead agency in accordance with the procedures adopted by the lead agency pursuant to Section 2774. If a question arises as to which public agency is the lead agency, any affected public agency, or the affected operator, may submit the matter to the board. The board shall notify in writing all affected public agencies and operators that the matter has been submitted, specifying a date for a public hearing. The board shall designate the public agency which shall serve as the lead agency, giving due consideration to the capability of the agency to fulfill adequately the requirements of this chapter and to an examination of which of the public agencies has principal permit responsibility.

Amended by Stats. 2017, Ch. 521, Sec. 35. (SB 809) Effective January 1, 2018.

(a)The reclamation plan shall be filed with the lead agency, on a form provided by the lead agency, by any person who owns, leases, or otherwise controls or operates on all or any portion of any mined lands and who plans to conduct surface mining operations on the lands.
(b)The reclamation plan shall include a chart identifying the page number, chapter, appendix, or other specific location in the reclamation plan where content meeting the requirements, as applicable, of Sections 2772, 2773, and 2773.3 and Article 1 (commencing with Section 3500) and Article 9 (commencing with Section 3700) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of

Regulations, is located.

(c)The reclamation plan shall include all of the following information and documents:
(1)The name and address of the operator and the names and addresses of any persons designated by the operator as an agent for the service of process.
(2)The anticipated quantity and type of minerals for which the surface mining operation is to be conducted.
(3)The proposed dates for the initiation and termination of the surface mining operation.
(4)The maximum anticipated depth of the surface mining operation.
(5)A

reclamation plan map or maps that shall include all of the following:

(A)Size and legal description of the lands that will be affected by the surface mining operation and the names and addresses of the owners of all surface interests and mineral interests in the lands.
(B)Clearly defined and accurately drawn property lines, setbacks, and the reclamation plan boundary.
(C)Existing topography and final topography depicted with contour lines drawn at appropriate intervals for the site’s conditions.
(D)Detailed geologic description of the area of the surface mining operation.
(E)Location of

railroads, utility facilities, access roads, temporary roads to be reclaimed, and any roads remaining for the approved end use.

(F)All maps, diagrams, or calculations that require preparation in accordance with the Professional Engineers Act (Chapter 7 (commencing with Section 6700) of Division 3 of the Business and Professions Code), the Geologist and Geophysicist Act (Chapter 12.5 (commencing with Section 7800) of Division 3 of the Business and Professions Code), or the Professional Land Surveyors’ Act (Chapter 15 (commencing with Section 8700) of Division 3 of the Business and Professions Code) shall be prepared by a California-licensed professional, shall include his or her license number and name, and shall bear the signature and seal of the licensee.
(6)A

description of and a plan for the type of surface mining to be employed and a time schedule that will provide for the completion of surface mining on each segment of the mined lands so that reclamation can be initiated at the earliest possible time on those portions of the mined lands that will not be subject to further disturbance by the surface mining operation.

(7)A description of the proposed use or potential uses of the mined lands after reclamation and evidence that all owners of a possessory interest in the land have been notified of the proposed use or potential uses.
(8)A description of the manner in which reclamation, adequate for the proposed use or potential uses, will be accomplished, including both of the following:
(A)A description of the manner in which known contaminants will be controlled and mining waste will be disposed.
(B)A description of the manner in which affected streambed channels and streambanks will be rehabilitated to a condition that minimizes erosion and sedimentation.
(9)An assessment of the effect of implementation of the reclamation plan on future mining in the area.
(10)A statement that the person submitting the reclamation plan accepts responsibility for reclaiming the mined lands in accordance with the reclamation plan.
(11)Any other information that the lead agency may require by ordinance.
(d)An item of information or a document required pursuant to subdivision (c) that has already been prepared as part of a permit application for the surface mining operation or as part of an environmental document prepared for the project pursuant to the California Environmental Quality Act (Division 13 (commencing with Section 21000)) may be included in the reclamation plan by reference, if that item of information or that document is attached to the reclamation plan when the lead agency submits the reclamation plan to the supervisor for review. To the extent the information, document, or component of a document referenced in the reclamation plan is used to meet the requirements of subdivision (c) or Section 2773 or 2773.3, the information, document, or component of a document shall become part of the reclamation plan and shall be subject to all other requirements of this article.
(e)Nothing in this section is intended to limit or expand the Division of Mine Reclamation’s authority or responsibility to review a document in accordance with the California Environmental Quality Act (Division 13 (commencing with Section 21000)).

Amended by Stats. 2017, Ch. 521, Sec. 36. (SB 809) Effective January 1, 2018.

(a)(1) Prior to approving a surface mining operation’s reclamation plan or plan amendment, the lead agency shall submit the reclamation plan or plan amendment to the supervisor for review. The reclamation plan or plan amendment shall be submitted to the supervisor as early as practicable in order to facilitate the lead agency’s review of the reclamation plan pursuant to the California Environmental Quality Act (Division 13 (commencing with Section 21000)). All documentation for the submission shall be submitted to the supervisor at one time.
(2)An item of information, document, or component of a document that has been prepared as part of a permit application for

the surface mining operation or as part of an environmental document prepared for the project pursuant to the California Environmental Quality Act (Division 13 (commencing with Section 21000)) shall be incorporated into the reclamation plan or plan amendment if it is used to satisfy the requirements of subdivision (c) of Section 2772, Sections 2773 and 2773.3, and Article 1 (commencing with Section 3500) and Article 9 (commencing with Section 3700) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, as applicable. If an item of information, document, or component of a document is incorporated, reference to the item shall be added to the chart required pursuant to subdivision (b) of Section 2772 and shall be properly indexed with the corresponding appendix reference and page numbers, if applicable. The item shall be included in an appendix to and shall become

part of the reclamation plan or plan amendment.

(3)The lead agency shall certify to the supervisor that the reclamation plan or plan amendment is a complete submission and is in compliance with all of the following:
(A)The applicable requirements of this chapter.
(B)Article 1 (commencing with Section 3500) and Article 9 (commencing with Section 3700) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, as applicable.
(C)The lead agency’s surface mining ordinance in effect at the time that the reclamation plan or plan amendment is submitted to the supervisor for review, except if the board is the lead agency.
(b)(1) The supervisor shall have 30 days from the receipt of a reclamation plan or plan amendment to notify the lead agency and operator if the submission is incomplete. An incomplete submission is one that does not meet the content requirements of Sections 2772, 2773, and 2773.3 and Article 1 (commencing with Section 3500) and Article 9 (commencing with Section 3700) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, as applicable. The supervisor’s notice shall specifically identify all aspects of the submission that are incomplete.
(2)The supervisor shall have 30 days after the date the supervisor is required to notify the lead agency if the submission is incomplete to prepare written comments on the

reclamation plan or plan amendment if the supervisor chooses.

(3)If the supervisor has issued a notice of incomplete submission pursuant to paragraph (1), the supervisor’s time to prepare written comments on the reclamation plan or plan amendment shall not commence until the supervisor receives each item identified in the notice. The supervisor’s time shall include any remaining time pursuant to paragraph (1) and the time allowed pursuant to paragraph (2).
(4)The lead agency shall review and evaluate written comments received from the supervisor relating to the reclamation plan or plan amendment within a reasonable amount of time.
(5)(A) The lead agency shall prepare a written response to the

supervisor’s comments received pursuant to paragraph (2) describing the disposition of the major issues raised by the comments. The lead agency shall submit its response to the supervisor at least 30 days prior to the intended approval of the reclamation plan or plan amendment. The lead agency’s response shall include either of the following:

(i)A description of how the lead agency proposes to adopt the supervisor’s comments to the reclamation plan or plan amendment.

(ii) A detailed description of the reasons why the lead agency proposes not to adopt the supervisor’s comments.

(B) Copies of any written comments received and responses prepared by the lead agency pursuant to subparagraph (A) shall be

forwarded to the operator.

(6)(A) The lead agency shall give the supervisor at least 30 days’ notice of the time, place, and date of the hearing at which the reclamation plan or plan amendment is scheduled to be approved by the lead agency.
(B)If no hearing is required by this chapter, the local ordinance, or other state law, the lead agency shall provide 30 days’ notice to the supervisor that the lead agency intends to approve the reclamation plan or plan amendment.
(7)(A) Within 30 days following the approval of the reclamation plan or plan amendment, the lead agency shall provide the supervisor notice of the approval. During that period, the Division of Mine

Reclamation retains all powers, duties, and authorities of this chapter. The lead agency shall provide, as soon as practicable but no later than 60 days after approval of the reclamation plan or plan amendment, certified copies of all maps, diagrams, or calculations, signed and sealed.

(B)No later than 60 days after the approval of the reclamation plan or plan amendment, the lead agency shall provide to the supervisor an official copy of the approved reclamation plan or plan amendment. The official copy shall incorporate all approved modifications to the reclamation plan or plan amendment and shall include an index showing any permit conditions of approval or binding mitigation measures adopted or certified pursuant to the California Environmental Quality Act (Division 13 (commencing with Section 21000)) that are necessary to meet the requirements of

subdivision (c) of Section 2772, Sections 2773 and 2773.3, and Article 1 (commencing with Section 3500) and Article 9 (commencing with Section 3700) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, as applicable. Those conditions of approval and mitigation measures shall be included in an appendix to the reclamation plan or plan amendment and shall be considered part of the reclamation compliance requirements and subject to the annual inspection requirements.

(c)To the extent there is a conflict between the comments of a trustee agency or a responsible agency that are based on that agency’s statutory or regulatory authority and the comments of other commenting agencies that are received by the lead agency pursuant to the California Environmental Quality Act (Division 13 (commencing with

Section 21000)) regarding a reclamation plan or plan amendments, the lead agency shall consider only the comments of the trustee agency or responsible agency.

(d)Nothing in this section is intended to limit or expand the Division of Mine Reclamation’s authority or responsibility to review a document in accordance with the California Environmental Quality Act (Division 13 (commencing with Section 21000)).

Added by Stats. 2000, Ch. 515, Sec. 2. Effective January 1, 2001.

(a)A reclamation plan by any person who owns, leases, or otherwise controls or operates on all, or any portion of any, mined lands within the boundaries of the San Gabriel Basin Water Quality Authority, and who plans to conduct surface mining operations on those lands, in addition to the information required pursuant to subdivision (c) of Section 2772, shall include a description of any programs necessary to monitor the effects of mining and reclamation operations on air, water, and soil quality, on the surrounding area, backfill characteristics, geologic conditions, and slope stability, similar to the California Environmental Quality Act document for the reclamation project.
(b)This section applies to activities otherwise subject to this chapter conducted within the boundaries of the San Gabriel Basin Water Quality Authority. To the extent of any conflict between this section and any other provision of this chapter, this section shall prevail.

Amended by Stats. 2017, Ch. 521, Sec. 37. (SB 809) Effective January 1, 2018.

(a)In addition to meeting the requirements of Section 2773.1, the financial assurance cost estimate required of a surface mining operation within the boundaries of the San Gabriel Basin Water Quality Authority for any one year shall be in an amount not less than that required to ensure reclamation of the disturbed areas is completed in accordance with the approved reclamation plan.
(b)This section applies to activities otherwise subject to this chapter conducted within the boundaries of the San Gabriel Basin Water Quality Authority. To the extent of any conflict between this section and any other provision of this chapter, this section shall

prevail.

Amended by Stats. 2009, Ch. 208, Sec. 3. (SB 833) Effective January 1, 2010.

(a)A lead agency, upon approval of a reclamation plan or an amendment to a reclamation plan, shall record a “Notice of Reclamation Plan Approval” with the county recorder. The notice shall read: “Mining operations conducted on the hereinafter described real property are subject to a reclamation plan approved by the ____ (lead agency), a copy of which is on file with the ____.”
(b)In addition to the information required by subdivision (a), the notice shall also include the name of the owner of record of the mine operation, the name of the lead agency, and the acknowledged signature of the lead agency representative.

Amended by Stats. 1990, Ch. 1097, Sec. 11.

(a)The reclamation plan shall be applicable to a specific piece of property or properties, shall be based upon the character of the surrounding area and such characteristics of the property as type of overburden, soil stability, topography, geology, climate, stream characteristics, and principal mineral commodities, and shall establish site-specific criteria for evaluating compliance with the approved reclamation plan, including topography, revegetation and sediment, and erosion control.
(b)By January 1, 1992, the board shall adopt regulations specifying minimum, verifiable statewide reclamation standards. Subjects for which standards shall be set include, but shall not be limited to, the following:
(1)Wildlife habitat.
(2)Backfilling, regrading, slope stability, and recontouring.
(3)Revegetation.
(4)Drainage, diversion structures, waterways, and erosion control.
(5)Prime and other agricultural land reclamation.
(6)Building, structure, and equipment removal.
(7)Stream protection.
(8)Topsoil salvage, maintenance, and redistribution.
(9)Tailing and mine waste management.

These standards shall apply to each mining operation, but only to the extent that they are consistent with the planned or actual subsequent use or uses of the mining site.

Amended by Stats. 2017, Ch. 521, Sec. 38. (SB 809) Effective January 1, 2018.

(a)Lead agencies shall require financial assurances of each surface mining operation to ensure reclamation is performed in accordance with the surface mining operation’s approved reclamation plan, as follows:
(1)A financial assurance mechanism may take the form of surety bonds executed by an admitted surety insurer, as defined in subdivision (a) of Section 995.120 of the Code of Civil Procedure, irrevocable letters of credit, trust funds, or other forms of financial assurance mechanisms specified by the board pursuant to subdivision (e) that the lead agency reasonably determines are adequate to perform reclamation in accordance with the surface mining operation’s approved

reclamation plan.

(2)Financial assurances shall remain in effect for the duration of the surface mining operation and any additional period until reclamation is completed.
(3)The amount of the financial assurance cost estimate required of a surface mining operation for any one year shall be reviewed and, if necessary, adjusted once each calendar year to account for new lands disturbed by surface mining operations, inflation, and reclamation of lands accomplished in accordance with the approved reclamation plan. An operator shall be required to replace an approved financial assurance mechanism to bond for the reclamation of the surface mining operation only if the financial assurance cost estimate identifies a need to increase the amount of the financial assurance

mechanism.

(4)Financial assurance cost estimates shall be submitted to the lead agency for review on a form developed by the supervisor and approved by the board. The form shall be subject to the requirements of the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code).
(5)Each financial assurance mechanism shall be made payable to the lead agency and the department. A financial assurance mechanism shall not be released without the consent of the lead agency and the department. A financial assurance mechanism that was approved by the lead agency prior to January 1, 1993, and was made payable to the State Geologist shall be considered payable to the department for purposes of this chapter. However, if

a surface mining operation has received approval of its financial assurance cost estimate from a public agency other than the lead agency, the lead agency shall deem those financial cost estimates adequate for purposes of this section, or shall credit them toward fulfillment of the financial cost estimate required by this section, if they are made payable to the public agency, the lead agency, and the department and otherwise meet the requirements of this section. In any event, if a lead agency and one or more public agencies exercise jurisdiction over a surface mining operation, the total amount of financial assurances required by the lead agency and the public agencies for any one year shall not exceed that amount that is necessary to perform reclamation of lands remaining disturbed. For purposes of this paragraph, a “public agency” may include a federal agency.

(b)(1) If the lead agency, or the board when acting as a lead agency, has evidence that an operator may be financially incapable of completing reclamation in accordance with its approved reclamation plan or that the operator may have abandoned the surface mining operation without completing reclamation, the lead agency or the board, when acting as a lead agency, shall conduct a public hearing to determine whether the operator is financially capable of completing reclamation in accordance with the approved reclamation plan or has abandoned the surface mining operation. The hearing shall be noticed to the operator and the supervisor at least 30 days prior to the hearing.
(2)If the lead agency or the board, following the public hearing conducted pursuant to

paragraph (1), determines that the operator is financially incapable of performing reclamation in accordance with its approved reclamation plan or has abandoned its surface mining operation without completing reclamation, either the lead agency or the supervisor shall do all of the following:

(A)Notify the operator by personal service or certified mail that the lead agency or the supervisor intends to take appropriate action to forfeit the financial assurances and specify the reasons for so doing.
(B)Proceed to take appropriate action to require forfeiture of the financial assurance mechanisms.
(C)Use the proceeds from the forfeited financial assurance mechanisms to conduct and complete reclamation in accordance with

the approved reclamation plan. If the surface mining operation cannot be reclaimed in accordance with its approved reclamation plan, or the financial assurance mechanisms are inadequate to reclaim in accordance with its approved reclamation plan, the lead agency or supervisor may use forfeited financial assurance mechanisms to reclaim or remediate mining disturbances as appropriate for the site conditions as determined by both the lead agency and the supervisor. The financial assurance mechanisms shall not be used for any other purpose. The operator is responsible for the costs of conducting and completing reclamation in accordance with the approved reclamation plan or a remediation plan developed pursuant to this section as determined appropriate by both the lead agency and the supervisor that are in excess of the proceeds from the forfeited financial assurance mechanisms.

(c)Financial assurances shall no longer be required of a surface mining operation, and shall be released, upon the written concurrence of the lead agency and the supervisor, which shall be forwarded to the operator and the institutions providing or holding the financial assurance mechanism, that reclamation has been completed in accordance with the approved reclamation plan. If a surface mining operation is sold or ownership is transferred to another person, the existing financial assurance mechanism shall remain in force and shall not be released by the lead agency and the supervisor until new financial assurance mechanisms are secured from the new owner and have been approved by the lead agency in accordance with Sections 2770, 2773.1, and 2773.4.

Within 90 days of the sale or transfer of a surface mining operation, the new operator shall submit an appropriate financial assurance mechanism, which may be the existing mechanism if the existing mechanism is payable in the event of the new operator’s financial incapability or abandonment of the surface mining operation, that is subject to review by the lead agency and the supervisor pursuant to subdivision (e) of Section 2773.4. Within 15 days of the sale or transfer of a surface mining operation, the new operator shall sign a new statement of reclamation responsibility in accordance with paragraph (10) of subdivision (c) of Section 2772.

(d)The lead agency shall have primary responsibility to seek forfeiture of the financial assurance mechanisms and to reclaim mine sites pursuant to subdivision (b). However, if the board is not

the lead agency pursuant to Section 2774.4, the supervisor may act to seek forfeiture of the financial assurance mechanisms and reclaim the mine sites pursuant to subdivision (b) only if both of the following occur:

(1)The financial incapability of the operator or the abandonment of the surface mining operation has come to the attention of the supervisor.
(2)The lead agency has been notified in writing by the supervisor of the financial incapability of the operator or the abandonment of the surface mining operation for at least 15 days, the lead agency has not taken appropriate measures to seek forfeiture

of the financial assurance mechanisms and reclaim the mine site, and one of the following has occurred:

(A)The lead agency has been notified in writing by the

supervisor that failure to take appropriate measures to seek forfeiture of the financial assurance mechanisms or to reclaim the mine site shall result in actions being taken against the lead agency under Section 2774.4.

(B)The supervisor determines that there is a violation that amounts to an imminent and substantial endangerment to the public health, safety, or to the environment.
(C)The lead agency notifies the supervisor in writing that its good faith attempts to seek forfeiture of the financial assurance mechanisms have not been successful.

The supervisor shall comply with subdivision (b) in seeking the forfeiture of financial assurance mechanisms and reclaiming mine sites.

(e)The board may adopt regulations specifying financial assurance mechanisms other than surety bonds, irrevocable letters of credit, and trust funds, which the board determines are reasonably available and adequate to ensure reclamation pursuant to this chapter, but these mechanisms shall not include financial tests or surety bonds executed by one or more personal sureties. These mechanisms may include reclamation bond pool programs.
(f)The board shall adopt or revise guidelines to implement this section as necessary. The guidelines are exempt from the requirements of the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code), and are not subject to review by the Office of Administrative Law.

Added by Stats. 1998, Ch. 643, Sec. 2. Effective January 1, 1999.

Notwithstanding Section 2773.1, a surety bond that was executed by any personal surety that was approved by the lead agency prior to February 13, 1998, to ensure that reclamation is performed in accordance with a reclamation plan approved by a lead agency prior to that date, may be utilized to satisfy the requirements of this chapter, if the amount of the financial assurance required to perform the approved reclamation plan, as amended or updated from time to time, does not change from the amount approved prior to February 13, 1998.

Added by Stats. 2006, Ch. 869, Sec. 22. Effective January 1, 2007.

The mineral owner and owner of the surface estate, if legally entitled to do so, shall allow access to the property on which the mining operation is located to any governmental agency or the agent of any company providing financial assurances in connection with the reclamation plan and expending those financial assurances for reclamation, in order that reclamation may be carried out by the governmental agency or company, in accordance with the reclamation plan.

Amended by Stats. 2017, Ch. 521, Sec. 40. (SB 809) Effective January 1, 2018.

(a)In addition to other reclamation plan requirements of this chapter and regulations adopted by the board pursuant to this chapter, a lead agency may not approve a reclamation plan for a surface mining operation for gold, silver, copper, or other metallic minerals or financial assurances for the operation, if the operation is located on, or within one mile of, any Native American sacred site and is located in an area of special concern, unless both of the following criteria are met:
(1)The reclamation plan requires that all excavations be backfilled and graded to do both of the following:
(A)Achieve

the approximate original contours of the mined lands prior to mining.

(B)Grade all mined materials that are in excess of the materials that can be placed back into excavated areas, including, but not limited to, all overburden, spoil piles, and heap leach piles, over the project site to achieve the approximate original contours of the mined lands prior to mining.
(2)The financial assurance cost estimates are sufficient in amount to provide for the backfilling and grading required by paragraph (1).
(b)For purposes of this section, the following terms have the following

meanings:

(1)“Native American sacred site” means a specific area that is identified by a federally recognized Indian Tribe, Rancheria or Mission Band of Indians, or by the Native American Heritage Commission, as sacred by virtue of its established historical or cultural significance to, or ceremonial use by, a Native American group, including, but not limited to, any area containing a prayer circle, shrine, petroglyph, or spirit break, or a path or area linking the circle, shrine, petroglyph, or spirit break with another circle, shrine, petroglyph, or spirit break.
(2)“Area of special concern” means any area in the California desert that is designated as Class C or Class L lands or as an Area of Critical Environmental Concern under the

California Desert Conservation Area Plan of 1980, as amended, by the United States Department of the Interior, Bureau of Land Management, pursuant to Section 1781 of Title 43 of the United States Code.

Amended by Stats. 2017, Ch. 521, Sec. 41. (SB 809) Effective January 1, 2018.

(a)(1) Prior to approving the financial assurance cost estimate for a new reclamation plan or adjustments to the financial assurance cost estimate based on an amendment to a reclamation plan, the lead agency shall submit the financial assurance cost estimate to the supervisor for review.
(2)The lead agency shall provide the supervisor with a determination that the financial assurance cost estimate submitted pursuant to paragraph (1) is adequate, complete, and consistent with Section 2773.1, Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, and the board’s financial assurance guidelines

adopted pursuant to subdivision (f) of Section 2773.1.

(3)All documentation submitted to the supervisor pursuant to this subdivision shall be submitted at one time.
(b)No later than 15 days after receiving a financial assurance cost estimate, the supervisor shall notify the lead agency and the operator if the submission is incomplete. An incomplete submission is one that does not meet the content requirements of Section 2773.1, Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, and the board’s financial assurance guidelines adopted pursuant to subdivision (f) of Section 2773.1. The supervisor’s notice shall specifically identify all aspects of the submission that are incomplete. The supervisor’s

time to review the financial assurance cost estimate shall commence upon the receipt of a submission that contains the aspects identified in the supervisor’s notice to the lead agency.

(c)(1) The supervisor shall have 45 days from the date of receipt of a complete financial assurance cost estimate to prepare written comments if the supervisor chooses.
(2)The lead agency shall evaluate written comments received from the supervisor relating to the financial assurance cost estimate within a reasonable amount of time. The lead agency shall prepare a written response to the supervisor’s comments describing the disposition of the major issues raised by the supervisor’s comments.
(3)The lead agency shall submit

its proposed response to the supervisor at least 30 days prior to approval of the financial assurance cost estimate. The lead agency’s response shall include either of the following:

(A)A description of how the lead agency proposes to adopt the

supervisor’s comments to the financial assurance cost estimate.

(B)A detailed description of the reasons why the lead agency proposes to not adopt the supervisor’s comments.
(4)Copies of any written comments received and responses prepared by the lead agency shall be forwarded to the operator.
(5)(A) If the lead agency, in its written response to the supervisor’s comments, proposes to not adopt the supervisor’s comments relating to the financial assurance cost estimate, the supervisor, within 15 days of receipt of the lead agency’s written response, may request in writing a consultation with the lead agency to discuss the supervisor’s comments and the lead agency’s response. The request

shall include an invitation to the operator to participate in the consultation. The consultation may be conducted in person, electronically, telephonically, or by any means convenient to the parties.

(B)If the supervisor requests a consultation pursuant to this subdivision, the lead agency shall not approve the financial assurance cost estimate until after consulting with the supervisor. The consultation shall occur not later than 30 days after the supervisor’s request unless an alternate timeframe is mutually agreed upon by the supervisor, lead agency, and operator.
(6)(A) The lead agency shall give the supervisor at least 30 days’ notice of the time, place, and date of the hearing at which the financial assurance cost estimate is scheduled to be approved by

the lead agency. If no hearing is required by this chapter, local ordinance, or other state law, then the lead agency shall provide 30 days’ notice to the supervisor that it intends to approve the financial assurance cost estimate.

(B)The lead agency shall send to the supervisor its final response to the supervisor’s comments within 30 days following its approval of the financial assurance cost estimate, during which time the Division of Mine Reclamation retains all of its powers, duties, and authority pursuant to this chapter.
(d)(1) (A) Within 30 days of an annual inspection being conducted pursuant to Section 2774, an operator shall provide an annual financial assurance cost estimate to the lead agency for review.

(B) If the lead agency fails to cause the inspection of the surface mining operation on the date requested by the operator pursuant to Section 2207 or on the date set by the lead agency pursuant to subdivision (c) of Section 2774, the operator shall provide an annual financial assurance cost estimate to the lead agency for review within 30 days of the applicable inspection date, unless the lead agency causes the inspection to occur within that time period, in which case the operator shall provide an annual financial assurance cost estimate to the lead agency within 30 days of the date of the inspection.

(2)(A) Within 60 days of receiving an operator’s annual financial assurance cost estimate, the lead agency shall do one of the following:
(i)Deny the financial assurance cost estimate pursuant to

paragraph (6).

(ii) Submit the financial assurance cost estimate to the supervisor for review.

(B) The lead agency shall provide the supervisor with a determination that the annual financial assurance cost estimate submitted is adequate, complete, and consistent with Section 2773.1, Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, and the board’s financial assurance guidelines adopted pursuant to subdivision (f) of Section 2773.1.

(3)All documentation submitted to the supervisor pursuant to this subdivision shall be submitted at one time.
(4)Within

15 days of receiving an annual financial assurance cost estimate, the supervisor shall notify the lead agency and the operator if the submission is incomplete. An incomplete submission is one that does not meet the content requirements of Section 2773.1, Article 11 (commencing with Section 3800) of Subchapter 1 of Chapter 8 of Division 2 of Title 14 of the California Code of Regulations, and the board’s financial assurance guidelines adopted pursuant to subdivision (f) of Section 2773.1. The supervisor’s notice shall specifically identify all aspects of the submission that are incomplete. The supervisor’s time to review the annual financial assurance cost estimate shall commence upon the receipt of a submission that contains the aspects identified in the supervisor’s notice to the lead agency.

(5)(A) Within 45 days of

receiving an operator’s complete annual financial assurance cost estimate from the lead agency, the

supervisor shall prepare written comments on the operator’s annual financial assurance cost estimate and provide the comments to the lead agency and the operator if the supervisor so chooses.

(B)(i) Within 30 days from receiving the supervisor’s written comments pursuant to this subdivision, the lead agency shall evaluate the written comments and provide the supervisor and operator its proposed response to the supervisor.

(ii) The lead agency shall submit its proposed response to the supervisor at least 30 days prior to approving the annual financial assurance cost estimate. The lead agency’s response shall include either of the following:

(I)A description of how the lead agency proposes

to adopt the

supervisor’s comments to the annual financial assurance cost estimate.

(II) A detailed description of the reasons why the lead agency proposes not to adopt the supervisor’s comments.

(iii) Copies of any written comments received and responses prepared by the lead agency pursuant to this subparagraph shall be provided to the operator.

(C)(i) If the lead agency, in its written response to the

supervisor’s comments, proposes to not adopt the supervisor’s comments concerning the annual financial assurance cost estimate, the supervisor, within 15 days of receipt of the lead agency’s written response, may request in writing a consultation with the lead agency to discuss the supervisor’s comments and the lead agency’s response. The request shall include an invitation to the operator to participate in the consultation. The consultation may be conducted in person, electronically, telephonically, or by any means convenient to the parties.

(ii) If the supervisor requests a consultation pursuant to this subparagraph, the lead agency shall not approve the annual financial assurance cost estimate until after consulting with the supervisor. The consultation shall occur not later than 30 days after the supervisor’s request

unless an alternate timeframe is mutually

agreed upon by the supervisor, lead agency, and operator.

(D)(i) Within 60 days of receiving the supervisor’s written comments, or of a consultation pursuant to this subdivision, whichever is later or the due date of the supervisor’s written comments if none are received, the lead agency shall approve or deny an operator’s annual financial assurance cost estimate.

(ii) The lead agency shall give the supervisor at least 30 days’ notice of the time, place, and date of the hearing at which the annual financial assurance cost estimate is scheduled to be approved by the lead agency.

(iii) If no hearing is required by this chapter, local ordinance, or other state law, the lead agency shall

provide 30 days’ notice to the supervisor that it intends to approve the annual financial assurance cost estimate.

(E)Within 30 days of the lead agency’s approval of the annual financial assurance cost estimate, the lead agency shall send the

supervisor its final response to the supervisor’s comments.

(6)If the lead agency determines an operator’s annual financial assurance cost estimate is inadequate, the lead agency shall specify the reasons for that determination. The operator shall have 30 days to appeal that denial pursuant to subdivision (e) of Section 2770 or provide a revised financial assurance cost estimate incorporating the suggested changes to the lead agency for approval by the lead agency pursuant to this section.
(e)(1) Within 30 days of the lead agency’s approval of a financial assurance cost estimate pursuant to this section, the operator shall provide the lead agency and the supervisor an appropriate financial assurance mechanism.
(2)(A) Within 15 days of receiving a financial assurance mechanism pursuant to this subdivision, or subdivision (c) of Section 2773.1 the lead agency and the supervisor shall review the financial assurance mechanism to determine if the type of mechanism, including the release instructions, meets the requirements of this chapter.
(B)Financial assurance mechanisms determined to be noncompliant with this chapter shall be returned to the operator with instructions on how to correct the type or release instructions of the financial assurance mechanism.
(3)By July 1, 2018, the board shall adopt forms to implement this subdivision as necessary. The forms shall be subject to the requirements of the Administrative Procedure Act (Chapter 3.5 (commencing with

Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code).

(f)The review and approval of financial assurances pursuant to this chapter shall not be considered a project for the purposes of the California Environmental Quality Act (Division 13 (commencing with Section 21000)).

Added by Stats. 2002, Ch. 1154, Sec. 2. Effective January 1, 2003. Operative April 7, 2003, pursuant to Stats. 2003, Ch. 3, Secs. 2 and 3.

Section 2773.3 does not apply to either of the following:

(a)Any surface mining operation in existence on January 1, 2003, for which the lead agency has issued final approval of a reclamation plan and the financial assurances prior to September 1, 2002.
(b)Any amended reclamation plan or financial assurances that are necessary for the continued operation or expansion of a surface mining operation in existence on January 1, 2003, that otherwise satisfies the requirements of subdivision (a).

Amended (as amended by Stats. 2018, Ch. 51, Sec. 16) by Stats. 2018, Ch. 349, Sec. 3. (AB 3257) Effective January 1, 2019.

(a)Every lead agency shall adopt ordinances in accordance with state policy that establish procedures for the review and approval of reclamation plans and financial assurances and the issuance of a permit to conduct surface mining operations, except that any lead agency without an active surface mining operation in its jurisdiction may defer adopting an implementing ordinance until the filing of a permit application. The ordinances shall establish procedures requiring at least one public hearing and shall be periodically reviewed by the lead agency and revised, as necessary, to ensure that the ordinances continue to be in accordance with state policy.
(b)(1) The lead agency shall cause surface mining operations to be inspected in intervals of no more than 12 months, solely to determine whether the surface mining operation is in compliance with this chapter. The lead agency shall cause an inspection to be conducted by a state-licensed geologist, state-licensed civil engineer, state-licensed landscape architect, state-licensed forester, or a qualified lead agency employee who has not been employed by the surface mining operation being inspected in any capacity during the previous 12 months, except that a qualified lead agency employee may inspect surface mining operations conducted by the local agency. All inspections shall be conducted using a form developed by the Division of Mine Reclamation and approved by the board that includes the professional licensing and disciplinary information of the person who conducted the inspection. The operator

shall be solely responsible for the reasonable cost of the inspection. The lead agency shall provide a notice of completion of inspection to the supervisor within 90 days of conducting the inspection. The notice shall contain a statement regarding the surface mining operation’s compliance with this chapter and a copy of the completed inspection form, and shall specify, as applicable, all of the following:

(A) Aspects of the surface mining operation, if any, that were found to be inconsistent with this chapter but were corrected before the submission of the inspection form to the supervisor.

(B) Aspects of the surface mining operation, if any, that were found to be inconsistent with this chapter but were not corrected before the submission of the inspection form to the supervisor.

(C) A statement describing the lead agency’s intended response to any aspects of the surface mining operation found to be inconsistent with this chapter but were not corrected before the submission of the inspection form to the supervisor.

(D) A statement as to whether the surface mining operation is out of compliance with an order to comply or stipulated order to comply issued by the lead agency.

(2)If the surface mining operation has a review of its reclamation plan, financial assurances, or an interim management plan pending under subdivision (b) or (h) of Section 2770, or an appeal pending before the board or lead agency governing body under subdivision (e) or (h) of Section 2770, the notice shall so indicate.

The lead agency shall forward to the operator a copy of the notice, a copy of the completed inspection form, and any supporting documentation, including, but not limited to, any inspection report prepared by the geologist, civil engineer, landscape architect, forester, or qualified lead agency employee who conducted the inspection.

(c)If an operator does not request an inspection date on the annual report filed pursuant to Section 2207 or if the lead agency is unable to cause the inspection of a given surface mining operation on the date requested by the operator, the lead agency shall provide the operator with a minimum of five days’ written notice of a pending inspection or a lesser time period if agreed to by the operator.
(d)(1) No later than December

31, 2017, the Division of Mine Reclamation shall establish a training program for all surface mine inspectors. The program shall be designed to include a guidance document, developed by the Division of Mine Reclamation, in consultation with the board and stakeholders, to provide instruction and recommendations to surface mine inspectors performing inspections pursuant to subdivision (b).

(2)The training program shall include inspection workshops offered by the Division of Mine Reclamation in different regions of the state to provide practical application of the guidance document material.
(3)On and after July 1, 2020, all inspectors shall have on file with the lead agency and the Division of Mine Reclamation a certificate of completion of an inspection workshop. An inspector shall

attend a workshop no later than five years after the date of his or her most recent certificate.

(4)The adoption of the guidance document by the Division of Mine Reclamation pursuant to this subdivision shall be subject to the requirements of the Administrative Procedure Act (Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code).

Amended by Stats. 2018, Ch. 349, Sec. 4. (AB 3257) Effective January 1, 2019.

(a)(1) Except as provided in subdivision (i) of Section 2770, if the lead agency or the supervisor determines, based upon an annual inspection pursuant to Section 2774, or otherwise confirmed by an inspection of the surface mining operation, that a surface mining operation is not in compliance with this chapter, the lead agency or the supervisor may issue a notice of that violation to the operator by personal service or certified mail. If the lead agency issues the notice, the lead agency shall send a copy of the notice to the supervisor. The notice shall include both of the following:

(A) A description of the violation.

(B) Actions the operator shall take to correct the violation.

(2)(A) If a lead agency or the supervisor determines that the time to correct the noticed violation will exceed 30 days, the lead agency and the operator may enter into a stipulated order to comply, with notice sent to the supervisor. If the supervisor initiated the enforcement action, the supervisor, after consulting with the lead agency, may enter into a stipulated order to comply with the operator. The lead agency may, but need not, join the stipulated order with the supervisor.
(B)A stipulated order to comply shall include a schedule and time for compliance that the lead agency or the supervisor, as applicable, determines is reasonable after taking into account the actions and legal

processes required to correct the violation.

(3)(A) If the operator does not comply with a notice issued pursuant to paragraph (1) within 30 days of being served the notice or commit to enter into a stipulated order to comply pursuant to paragraph (2) within 30 days of being served the notice, the lead agency or the supervisor may issue an order to comply by personal service or certified mail requiring the operator to comply with this chapter or, if the operator does not have an approved reclamation plan or financial assurances, cease all further surface mining activities. A lead agency shall, at the time of issuing an order to comply, provide a copy to the supervisor.
(B)An order to comply issued pursuant to this paragraph shall take effect 30 days following

the service of the order to comply unless within those 30 days the operator appeals the order to comply and requests a hearing before the lead agency, if the lead agency issued the order, or the board, if the supervisor issued the order. An order to comply issued pursuant to this paragraph shall specify all of the following:

(i)Which aspects of the surface mining operation are inconsistent with this chapter.

(ii) A time for compliance that the lead agency or supervisor determines is reasonable, taking into account the seriousness of the alleged violation and any good faith efforts to comply with applicable requirements.

(iii) The actions and legal processes required to correct the alleged violation.

(C) An appeal filed pursuant to subparagraph (B) shall be noticed and heard at a public hearing within 45 days of the filing of the appeal or a longer period as may be mutually agreed upon by the operator and the lead agency, if the lead agency issued the order, or the operator and the supervisor, if the supervisor issued the order.

(b)[Reserved]
(c)An operator who violates or fails to comply with an order to comply issued under subdivision (a) after the order’s effective date or who fails to submit a report or pay annual fees to the supervisor or lead agency as required by Section 2207, shall be subject to an order by the lead agency or the supervisor imposing an administrative penalty of not more than five

thousand dollars ($5,000) per day, assessed from the original date of noncompliance with this chapter, including Section 2207, or from the date of the inspection when the violation was identified, at the discretion of the issuer of the notice of that violation. The penalty may be imposed administratively by the lead agency or the supervisor. In determining the amount of the administrative penalty, the lead agency or the supervisor shall take into consideration the nature, circumstances, extent, and gravity of the violation or violations, any prior history of violations, the degree of culpability, economic savings, if any, resulting from the violation, and any other matters justice may require. Orders setting administrative penalties shall become effective upon issuance of the assessment and payment shall be made to the lead agency or the supervisor within 30 days, unless the operator petitions

the legislative body of the lead agency, the board, or the superior court for review as provided in Section 2774.2. An order shall be served by personal service or by certified mail upon the operator. Penalties collected by the supervisor shall not be used for purposes other than to cover the reasonable costs incurred by the department in implementing this chapter or Section 2207.

(d)(1) An operator who violates or fails to comply with an order to comply issued pursuant to paragraph (3) of subdivision (a) or a stipulated order to comply entered into pursuant to paragraph (2) of subdivision (a) after the order’s effective date shall be removed from the list published by the Division of Mine Reclamation pursuant to subdivision (b) of Section 2717.
(2)If after a

public hearing the board or lead agency denies an appeal by the operator pursuant to subparagraph (C) of paragraph (3) of subdivision (a), the operator shall be removed 10 working days following the denial of the appeal from the list published by the Division of Mine Reclamation pursuant to subdivision (b) of Section 2717.

(3)If the operator enters into a stipulated order to comply between the operator and the lead agency, if the lead agency issued the order, or the operator and the supervisor, if the supervisor issued the order, within 10 working days of the denial of the appeal and the stipulated order to comply is consistent with the order to comply upheld by the board or lead agency and includes a stipulated schedule for compliance, the operator shall remain on the list published by the Division of Mine Reclamation pursuant to

subdivision (b) of Section 2717.

(4)Issuance of a notice pursuant to paragraph (1) of subdivision (a) or an order to comply or stipulated order to comply pursuant to paragraph (2) or (3) of subdivision (a) shall not disqualify an operator from eligibility for placement on the list published by the Division of Mine Reclamation pursuant to subdivision (b) of Section 2717, except in cases where an operator has failed to submit a financial assurance cost estimate to the lead agency or a financial assurance mechanism to the lead agency and supervisor, in accordance with Section 2773.4.
(e)If the lead agency or the supervisor determines that the surface mine is not in compliance with this chapter, so that the surface mine presents an imminent and substantial endangerment to the

public health or the environment, the lead agency or the Attorney General, on behalf of the supervisor, may seek an order from a court of competent jurisdiction enjoining that operation.

(f)Upon a complaint by the supervisor, the department, or the board, the Attorney General may bring an action to recover administrative penalties under this section, and penalties under Section 2207, in any court of competent jurisdiction in this state against any person violating any provision of this chapter or Section 2207, or any regulation adopted pursuant to this chapter or Section 2207. The Attorney General may bring this action on his or her own initiative if, after examining the complaint and the evidence, he or she believes a violation has occurred. The Attorney General may also seek an order from a court of competent jurisdiction compelling the

operator to comply with this chapter and Section 2207.

(g)(1) The lead agency has primary responsibility for enforcing this chapter and Section 2207. In cases where the board is not the lead agency pursuant to Section 2774.4, enforcement actions may be initiated by the supervisor pursuant to this section only after the violation has come to the attention of the supervisor and either of the following occurs:

(A) The lead agency has been notified by the supervisor in writing of the violation for at least 30 days, and has not taken appropriate enforcement action, which may include failing to issue an order to comply within a reasonable time after issuing a notice of violation.

(B) The supervisor

determines that there is a violation that amounts to an imminent and substantial endangerment to the public health or safety, or to the environment.

(2)The supervisor shall comply with this section in initiating enforcement actions.
(h)Remedies under this section are in addition to, and do not supersede or limit, any and all other remedies, civil or criminal.

Amended by Stats. 2017, Ch. 521, Sec. 44. (SB 809) Effective January 1, 2018.

(a)Within 30 days of the issuance of an order setting administrative penalties under subdivision (c) of Section 2774.1, the operator may petition the legislative body of the lead agency, if the lead agency has issued the order, or the board for orders issued by the supervisor, for review of the order. If the operator does not petition for review within the time limits set by this subdivision, the order setting administrative penalties shall not be subject to review by any court or agency.
(b)The legislative body of the lead agency or the board shall notify the operator by personal service or certified mail whether it will review the order setting administrative penalties. In reviewing

an order pursuant to this section, the record shall consist of the record before the lead agency or the supervisor and any other relevant evidence which, in the judgment of the legislative body or the board, should be considered to effectuate and implement the policies of this chapter.

(c)The legislative body or the board may affirm, modify, or set aside, in whole or in part, by its own order, an order of the lead agency or the supervisor setting administrative penalties reviewed by the legislative body or the board pursuant to this section.
(d)An order of the legislative body or the board issued under subdivision
(c)shall become effective upon its issuance unless the operator petitions the superior court for review as provided in subdivision (e). An order shall be served by personal service or by certified mail upon the operator. Payment of an administrative penalty that is specified in an order issued pursuant to subdivision (c) shall be made to the lead agency or the supervisor within 30 days of service of the order. However, the payment shall be held in an interest bearing impound account pending the resolution of a petition for review filed pursuant to subdivision (e).
(e)An operator aggrieved by an order of the legislative body or the board issued pursuant to subdivision (c) may obtain review of the order by filing in the superior court a petition for writ of mandate within 30 days following the issuance of the order. An operator aggrieved by an

order of a lead agency or the supervisor setting administrative penalties pursuant to subdivision (c) of Section 2774.1, for which the legislative body or board denies review, may obtain review of the order in the superior court by filing in the court a petition for writ of mandate within 30 days following the denial of review. The provisions of Section 1094.5 of the Code of Civil Procedure shall govern judicial proceedings pursuant to this subdivision, except that in every case the court shall exercise its independent judgment. If the operator does not petition for a writ of mandate within the time limits set by this subdivision, an order of the board or the legislative body shall not be subject to review by any court or agency.

(f)(1) After the expiration of the time to petition for review pursuant to subdivision (a)

or (e), the supervisor or the board acting as the lead agency may apply to the small claims court or the superior court, depending on the jurisdictional amount, in the county where the administrative penalty was imposed for a judgment to collect the unpaid administrative penalty imposed pursuant to subdivision (c) of Section 2774.1. The application shall include all of the following:

(A) The order setting the administrative penalty pursuant to subdivision (c) of Section 2774.1.

(B) A notice to the operator of the right to petition for review of the order.

(C) Either of the following:

(i)A declaration from the board that no petition was made or that

the board declined to review the petition.

(ii) A copy of the final order of the board.

(2)An application submitted pursuant to this subdivision shall constitute a sufficient showing to warrant the issuance of the judgment. The court clerk shall enter the judgment immediately in conformity with the application.
(3)The judgment entered pursuant to this subdivision shall have the same force and effect as, and shall be subject to all the provisions of law relating to, a judgment in a civil action and may be enforced in the same manner as any other judgment of the court. The court shall make enforcement of the judgment a priority.

Amended by Stats. 1987, Ch. 975, Sec. 3.

The board shall review lead agency ordinances which establish permit and reclamation procedures to determine whether each ordinance is in accordance with state policy, and shall certify the ordinance as being in accordance with state policy if it adequately meets, or imposes requirements more stringent than, the California surface mining and reclamation policies and procedures established by the board pursuant to this chapter.

Amended by Stats. 2017, Ch. 521, Sec. 45. (SB 809) Effective January 1, 2018.

(a)The board shall exercise some or all of a lead agency’s powers under this chapter pursuant to subdivision (c), except for permitting authority and vested rights determinations, if the board finds that a lead agency has done any of the following:
(1)Approved reclamation plans or financial assurance mechanisms that are not consistent with this chapter.
(2)Failed to inspect or cause the inspection of surface mining operations as required by this chapter.
(3)Failed to seek forfeiture of financial assurances and to carry out reclamation of surface mining operations

as required by this chapter.

(4)Failed to take appropriate enforcement actions as required by this chapter.
(5)Intentionally misrepresented the results of inspections required under this chapter.
(6)Failed to submit information to the Division of Mine Reclamation as required by this chapter.
(b)The board shall conduct a public hearing no sooner than three years after the board has taken action pursuant to subdivision (a) to determine if a lead agency has corrected its deficiencies in implementing and enforcing this chapter and the rules and regulations adopted pursuant to this chapter. If the board finds the lead agency has corrected some or

all of its deficiencies in implementing and enforcing this chapter, the board shall restore to the lead agency some or all of the powers assumed by the board pursuant to subdivision (a).

(c)(1) Before taking any action pursuant to subdivision (a), the board shall first notify the lead agency of the identified deficiencies and allow the lead agency 45 days to provide a response to the board on the identified deficiencies. The board may review the lead agency’s response at a regularly scheduled meeting.
(2)(A) If the board is not satisfied with the lead agency’s response, the board shall hold a public hearing within the lead agency’s area of jurisdiction, upon a 45-day written notice given to the public in at least one newspaper of general

circulation within the city or county and directly mailed to the lead agency and to all operators within the lead agency’s jurisdiction who have submitted reports as required by Section 2207.

(B)At the hearing, the board shall determine if the lead agency has engaged in the conduct described in subdivision (a). If the board finds that the lead agency has engaged in conduct described in subdivision (a), the board shall do either of the following:
(i)Require the lead agency to develop a remedial plan to correct the noted deficiencies. The remedial plan shall describe specific objectives and corresponding processes designed to address, at a minimum, the noted deficiencies and a time that the remedial plan will be fully implemented. The board shall set a hearing to review the

completion of the remedial plan consistent with paragraph (2) and subdivisions (d) and (e).

(ii) Take immediate action pursuant to subdivision (a).

(d)Affected operators and interested persons have the right at the public hearing to present oral and written evidence on the matter being considered. At the public hearing, the board may place reasonable limits on the right of affected operators and interested persons to question and solicit testimony.
(e)(1) If the board decides to take action pursuant to subdivision (a) and exercise some or all of a lead agency’s powers under this chapter, except for permitting authority and vested rights determinations, the board, based on the record of the public hearing,

shall adopt written findings that explain all of the following:

(A) The action to be taken by the board.

(B) Why the board decided to take the action.

(C) Why the action is authorized by and meets the requirements of subdivision (a).

(2)In addition, the board’s findings shall address the significant issues raised, or written evidence presented, by affected operators, interested persons, the lead agency, or the Division of Mine Reclamation. The transcript of testimony and exhibits, together with all papers and requests filed in the proceedings, shall constitute the exclusive record for decision by the board.
(f)If the board finds at the hearing held pursuant to paragraph (2) of subdivision (c) that the lead agency has not completed the remedial plan prepared pursuant to clause (i) of subparagraph (B) of paragraph (2) of subdivision (c) to the board’s satisfaction, the board shall follow the procedures set forth in paragraph (2) of subdivision (c) and subdivisions (d) and (e). If the board finds at the hearing held pursuant to paragraph (2) of subdivision (c) that the lead agency has completed the remedial plan prepared pursuant to clause (i) of subparagraph (B) of paragraph (2) of subdivision (c) to the board’s satisfaction, the board shall conclude the action it has taken pursuant to this section.
(g)The lead agency, any affected operator, or any interested person who has presented oral or written evidence at the public hearing

before the board pursuant to subdivision (d) may obtain review of the board’s action taken pursuant to subdivision (a) by filing in the superior court a petition for writ of mandate within 30 days following the issuance of the board’s decision. Section 1094.5 of the Code of Civil Procedure governs judicial proceedings pursuant to this subdivision, except that in every case the court shall exercise its independent judgment. If a petition for a writ of mandate is not filed within the time limits set by this subdivision, the board’s action under subdivision (a) shall not be subject to review by any court or agency.

Amended by Stats. 1987, Ch. 975, Sec. 4.

(a)If, upon review of an ordinance, the board finds that it is not in accordance with state policy, the board shall communicate the ordinance’s deficiencies in writing to the lead agency. Upon receipt of the written communication, the lead agency shall have 90 days to submit a revised ordinance to the board for certification as being in accordance with state policy. The board shall review the lead agency’s revised ordinance for certification within 60 days of its receipt. If the lead agency does not submit a revised ordinance within 90 days, the board shall assume full authority for reviewing and approving reclamation plans submitted to the lead agency until the time the lead agency’s ordinances are revised in accordance with state policy.
(b)If, upon review of a lead agency’s revised ordinance, the board finds the ordinance is still not in accordance with state policy, the board shall again communicate the ordinance’s deficiencies in writing to the lead agency. The lead agency shall have a second 90-day period in which to revise the ordinance and submit it to the board for review. If the board again finds that the revised ordinance is not in accordance with state policy or if no revision is submitted, the board shall assume full authority for reviewing and approving reclamation plans submitted to the lead agency until the time the lead agency’s ordinances are revised in accordance with state policy.
(c)In any jurisdiction in which the lead agency does not have a certified ordinance, no person shall initiate a surface mining operation unless a reclamation plan has been submitted to, and approved by, the board. Any reclamation plan, approved by a lead agency under the lead agency’s ordinance which was not in accordance with state policy at the time of approval, shall be subject to amendment by the board or under the ordinance certified by the board as being in accordance with state policy.
(d)Reclamation plans approved by the board pursuant to this section shall not be subject to modification by the lead agency at a future date but may be amended by the board. Reclamation plans approved by the board shall be remanded to the lead agency upon certification of the lead agency’s ordinance, and the lead agency shall approve the reclamation plan as approved by the board, except that a subsequent amendment as may be agreed upon between the operator and the lead agency may be made according to this chapter. No additional public hearing shall be required prior to the lead agency’s approval. Nothing in this section shall be construed as authorizing the board to issue a permit for the conduct of mining operations.

Added by Stats. 1975, Ch. 1131.

(a)An applicant whose request for a permit to conduct surface mining operations in an area of statewide or regional significance has been denied by a lead agency, or any person who is aggrieved by the granting of a permit to conduct surface mining operations in an area of statewide or regional significance, may, within 15 days of exhausting his rights to appeal in accordance with the procedures of the lead agency, appeal to the board.
(b)The board may, by regulation, establish procedures for declining to hear appeals that it determines raise no substantial issues.
(c)Appeals that the board does not decline to hear shall be scheduled and heard at a public hearing held within the jurisdiction of the lead agency which processed the original application within 30 days of the filing of the appeal, or such longer period as may be mutually agreed upon by the board and the person filing the appeal. In any such action, the board shall not exercise its independent judgment on the evidence but shall only determine whether the decision of the lead agency is supported by substantial evidence in the light of the whole record. If the board determines the decision of the lead agency is not supported by substantial evidence in the light of the whole record it shall remand the appeal to the lead agency and the lead agency shall schedule a public hearing to reconsider its action.

Amended by Stats. 2006, Ch. 538, Sec. 560. Effective January 1, 2007.

(a)No person who has obtained a vested right to conduct surface mining operations prior to January 1, 1976, shall be required to secure a permit pursuant to this chapter as long as the vested right continues and as long as no substantial changes are made in the operation except in accordance with this chapter. A person shall be deemed to have vested rights if, prior to January 1, 1976, the person has, in good faith and in reliance upon a permit or other authorization, if the permit or other authorization was required, diligently commenced surface mining operations and incurred substantial liabilities for work and materials necessary for the surface mining operations. Expenses incurred in obtaining the enactment of an ordinance in relation to a particular operation or the issuance of a permit shall not be deemed liabilities for work or materials.
(b)The reclamation plan required to be filed under subdivision (b) of Section 2770, shall apply to operations conducted after January 1, 1976, or to be conducted.
(c)Nothing in this chapter shall be construed as requiring the filing of a reclamation plan for, or the reclamation of, mined lands on which surface mining operations were conducted prior to January 1, 1976.

Added by Stats. 1975, Ch. 1131.

Amendments to an approved reclamation plan may be submitted detailing proposed changes from the original plan. Substantial deviations from the original plan shall not be undertaken until such amendment has been filed with, and approved by, the lead agency.

Amended by Stats. 2017, Ch. 521, Sec. 46. (SB 809) Effective January 1, 2018.

(a)The construction and operation of a renewable energy generation facility on disturbed mined lands, including all foundations and other installations, facilities, buildings, accessory structures, and other improvements to the land that are related to the generation of energy, shall be considered an interim use for the purposes of this chapter and shall not require an amendment to an approved reclamation plan if all of the following criteria are met:
(1)The renewable energy generation facility will not adversely affect the completion of reclamation in accordance with the surface mining operation’s approved reclamation plan.
(2)The permit conditions of the renewable energy generation facility address and eliminate any potentially adverse impacts on the surface mining operation.
(3)The operating permit for the renewable energy generation facility includes both of the following:
(A)An approved closure and decommissioning plan that will not affect the manner in which reclamation will be achieved pursuant to this chapter.
(B)A separate financial assurance mechanism that the lead agency determines to be sufficient to perform the removal of the renewable energy generation facility.
(4)The closure and decommissioning of the renewable energy generation facility will

occur prior to the later of the following:

(A)The expiration of the use permit for the surface mining operation.
(B)The completion of reclamation in accordance with the surface mining operation’s approved reclamation plan.
(5)All required permits for the construction and related land improvements have been approved by a public agency in accordance with the applicable provisions of state law and locally adopted plans and ordinances, including, but not limited to, the California Environmental Quality Act (Division 13 (commencing with Section 21000)).
(b)(1) Prior to approving an operating permit for a renewable energy generation

facility subject to this section, the lead agency shall submit the operating permit application with all the associated maps and plans to the supervisor for review.

(2)The supervisor shall have 30 days from the receipt of the application with associated documents to prepare written comments if the supervisor chooses.
(3)The supervisor may provide comments relating to whether the renewable energy generation facility meets the criteria set forth in paragraphs (1) to (4), inclusive, of subdivision (a).
(4)The lead agency shall prepare a written response to the supervisor’s comments and submit its response to the supervisor at least 30 days prior to the approval of the operating permit for the renewable energy generation

facility.

(c)Copies of all approved permits and associated documents shall be submitted to the lead agency and the supervisor as an addendum to the approved reclamation plan no less than 30 days prior to the commencement of land improvements associated with the renewable energy generation facility.
(d)For purposes of this section, “renewable energy generation facility” means a solar photovoltaic, solar thermal under 50 megawatts, or wind energy generation facility.

Amended by Stats. 2017, Ch. 521, Sec. 47. (SB 809) Effective January 1, 2018.

(a)An operator who has failed to properly report a mine’s mineral production or mine status in any previous year, pursuant to the annual reporting requirement in Section 2207, prior to January 1, 2012, may attach corrected annual reports to the 2012 annual report so long as the corrected annual reports are submitted on or before July 1, 2013, and if the lead agency confirms in writing to the department all of the following:
(1)The operator has provided written notification to the lead agency and the supervisor of their intention to continue surface mining operations.
(2)The operator has an existing, valid permit or a

vested right to conduct surface mining operations pursuant to Section 2776.

(3)(A) The operator’s reclamation plan has been approved and is in compliance with this chapter, the surface mining operation is in compliance with the approved reclamation plan or applicable compliance order issued pursuant to this chapter, the surface mining operation has an approved financial assurance in place that the lead agency determines is adequate for reclamation pursuant to the approved reclamation plan, and the surface mining operation has been inspected by the lead agency as provided by Section 2774.
(B)The Division of Mine Reclamation may enter any mine site for which an operator has requested a correction of mine status or a return to idle status pursuant to this

section in order to conduct an inspection.

(4)The operator has demonstrated that there are commercially useful mineral reserves remaining at the surface mining operation.
(5)Unpaid fees for years during which the operation’s status was not properly reported have been paid to the department.
(6)The operator provides evidence to support any modified production reported on corrected annual reports.
(b)A mining operation that became idle, as defined in Section 2727.1, that failed to prepare and have approved an interim management plan and was thus considered abandoned pursuant to paragraph (6) of subdivision (h) of Section 2770 prior to January 1, 2013, may, without

prejudice, be returned to idle status at the request of the operator if an interim management plan is approved by July 1, 2013, and upon lead agency verification of compliance with subdivision (a).

(c)The mine operator shall be responsible for the reasonable

costs of an inspection conducted by the Division of Mine Reclamation pursuant to subparagraph (B) of paragraph (3) of subdivision (a).

Amended by Stats. 2017, Ch. 521, Sec. 48. (SB 809) Effective January 1, 2018.

(a)Reclamation plans, reports, applications, and other documents submitted pursuant to this chapter are public records, unless it can be demonstrated to the satisfaction of the lead agency that the release of that information, or part thereof, would reveal production, reserves, or rate of depletion entitled to protection as proprietary information. The lead agency shall identify such proprietary information as a separate part of the application. Proprietary information shall be made available only to the supervisor and to persons authorized in writing by the operator and by the owner.
(b)A copy of all reclamation plans, reports, applications, and other

documents submitted pursuant to this chapter shall be furnished to the supervisor by lead agencies on request.

Added by Stats. 1975, Ch. 1131.

Whenever one operator succeeds to the interest of another in any incompleted surface mining operation by sale, assignment, transfer, conveyance, exchange, or other means, the successor shall be bound by the provisions of the approved reclamation plan and the provisions of this chapter.