Allocations made pursuant to Section 2453 shall be made on the basis of the following:
existing grade separation, no allocation shall be made unless the railroad agrees to contribute 10 percent of the cost of the project.
inclusive, a single project in excess of five million dollars ($5,000,000), but not exceeding twenty million dollars ($20,000,000), shall be considered without specific legislative authority, if the project (A) is included in the Public Utilities Commission’s priority list of projects scheduled to be funded, (B) eliminates the need for future related grade separation projects, (C) provides projected cost savings of at least 50 percent to the state or local jurisdiction, or both of them, by eliminating the need for future projects, and (D) alleviates traffic and safety problems or provides improved rail service not otherwise possible. Projects approved pursuant to this subdivision shall be funded over a multiyear period, not to exceed five years, and the allocation for any one of those years shall not exceed the amount prescribed by subdivision (c) for a single project.
fiscal year for grade separation projects may be used for the purposes of this subdivision. An agency that has received an allocation for a project approved pursuant to this subdivision shall not be eligible for an allocation for another project under this subdivision for a period of 10 years from the date of approval of that project. However, if funds are available for allocation, as determined by the Department of Transportation, an agency may be eligible for an allocation for another project.
provision of law, when the state or a local agency uses state funds in financing a portion of project costs, the railroad contribution, to the extent determined pursuant to this section, shall be calculated based on the cost of the grade separation only, and not the cost of any other part of the project.
Cite this section